The stormwater drainage and waterlogging relief project on Amirik Street in Koye Moshaver was carried out. The Arak Municipality’s operational teams, over one week of construction activity, carried out geometric corrections to the curbs and also installed 70 meters of new curbing. In this project, the worn-out stormwater drainage pipes at the intersection of Amir and Reshadat streets were replaced, and 45 concrete slabs were installed to secure the curbs of the mentioned passageway and ensure the safe passage of citizens. Finally, after the installation of the new curbs was completed, 70 tons of asphalt were spread and the street’s geometric slope was corrected to properly direct stormwater toward the curbs, thereby resolving the waterlogging problem in this passageway.